Contract 883 - Cantonment update February
Circle Line 6 Construction
by SG MRT Construction
2M ago
  15 February 2024 - Exit 2 as of mid-February. More sections of the station are beginning to take shape with the surface structures pushing through. The station achieved basic structural completion (BSC) in the middle of 2023, with the exits likely to follow this coming year. Check on after the jump for more pictures! June 2023 - Achieving basic structural completion. Source: LinkedIn June 2023 - Achieving basic structural completion. Source: LinkedIn June 2023 - Achieving basic structural completion. Source: LinkedIn As with Keppel station, Canton ..read more
Visit website
C885 - Prince Edward Road update February 2024
Circle Line 6 Construction
by SG MRT Construction
2M ago
  11 February 2024 - A view of the concrete structure of Exit 1 seen from Shenton Way. Works at Prince Edward Road station have been progressing with more of the surface structures of the station becoming visible. Eventually, there will be approximately 3 ancillary buildings for ventilation & cooling towers, in addition to the station's 2 exits. In addition, there is also a mid-tunnel emergency exit along Keppel Road that has since taken shape. This exit would allow for evacuation from the stacked bored tunnels that run between Prince Edward Road and Cantonment stations in th ..read more
Visit website
C882 - Keppel update February 2024
Circle Line 6 Construction
by SG MRT Construction
2M ago
  11 February 2024 - A view eastwards along Keppel Road. 11 February 2024 - More permanent structures can now be seen at the surface level. It has been a month now since work to "Close the Circle" by connecting tunnels and tracks from Keppel to HarbourFront stations has begun. While temporary changes to the service patterns of the main line were implemented, work continues to make progress over at Contract 882's Keppel station site. We take a look at how the site has changed since we last checked in at the end of 2023. June 2023 - A view of the station's platform ..read more
Visit website
Upcoming temporary CCL service pattern changes 20 Jan - 24 May 2024
Circle Line 6 Construction
by SG MRT Construction
3M ago
  11 January 2024 - A banner at Buona Vista station informing passengers about the upcoming temporary service changes. Its less than a week away to the upcoming temporary Circle Line (CCL) service pattern changes which will commence this Saturday (20 January 2024). What are the changes? Why are the changes needed? And what are the works being done that necessitate these changes? We'll delve into these questions in this post, more after the jump. What are the changes?1. In summary, there will not be any through service from Dhoby Ghaut or Marina Bay to HarbourFront. Passengers wi ..read more
Visit website
CCL6 year-end update 2023
Circle Line 6 Construction
by SG MRT Construction
4M ago
  Contract 882's Keppel station site. Top : 27 April 2023 Bottom : 9 December 2023 Contract 883's Cantonment station site. Top : 30 December 2022 Bottom : 9 December 2023 Contract 885's Prince Edward Road station site along Shenton Way. Top : 4 August 2023 Bottom : 9 December 2023 Contract 886's cut & cover tunnel sites. Top : 27 April 2023 Bottom : 9 December 2023 It has been a big year for the Circle Line 6 (CCL6) project with the station structures of the 3 new stations now substantially complete. We take a look back at the progress made over ..read more
Visit website
CCL6 Newsletter 2023
Circle Line 6 Construction
by SG MRT Construction
5M ago
  Today, the Land Transport Authority (LTA) released the fifth Circle Line 6 newsletter. In this edition, maps featuring the stations renumbered exits were included in. Several small general updates are also provided within. In summary, station structural works are substantially completed with the works now shifting towards the construction of station exits at street level, the architectural components and mechanical installations. You can read the newsletter here. This is a blog-only post ..read more
Visit website
C882 - Keppel update November 2023
Circle Line 6 Construction
by Jon
5M ago
  25 November 2023 - A view of the lift shaft for the exit next to the eastbound carriageway of Keppel Road. Ahead of major disruptive work for the Circle Line next year, we pay the Keppel station a visit to check in on progress made. Backfilling work is continuing with a significant difference noted over the station's roof slab. In our previous update in August, parts of the concrete roof slab could still be seen exposed to the elements. These have since been covered over with soil and demolition work is ongoing for the earth retaining & stabilising system (ERSS) - a system ..read more
Visit website
C886 - C&C Tunnels & Trackworks update October 2023
Circle Line 6 Construction
by Jon
6M ago
  14 October 2023 - An overview of the contract 886 site. Besides getting a great view of Prince Edward Road station, the team also enjoyed great views of the cut & cover tunnels linking Prince Edward Road and Marina Bay stations. This also includes a section of tunnels splitting off the main line known as the turnback tunnels. It is here that the trackworks contractor is given a site to work from, known as the Temporary Staging Area (TSA). TunnelsThe structural works of the tunnels are largely completed with demolition of the capping beam continuing. This allows a smooth la ..read more
Visit website
C885 - Prince Edward Road update October 2023
Circle Line 6 Construction
by Jon
6M ago
  14 October 2023 - An aerial view of the Prince Edward Road station site. Recently the SGMC team visited the Westin Hotel and took in a bit of a view of the downtown area. We had the opportunity to admire the views of Prince Edward Road. It seems that they have since completed the station roof slab and covered up most of the underground structures. Some surface-level elements are now becoming more apparent. But we'll let the pictures do the talking. 14 October 2023 - A view of the western end of the station box where the launch shaft used to be. 14 October 20 ..read more
Visit website
C883 - LTA updates during Tok Panjang event
Circle Line 6 Construction
by Jon
8M ago
  16 September 2023 This past weekend, Tanjong Pagar - Tiong Bahru CCC organised a Tok Panjang (long table feast) event at Blair Road on 16th September 2023. As part of the event, the Land Transport Authority (LTA) had set up a booth to reach out to residents and provide them with updates on the construction progress of Cantonment station. 16 September 2023 - A view of the displays at the LTA booth of the event. 16 September 2023 - Display on the benefits of CCL6, 16 September 2023 - Display on the construction work updates. 16 September 2023 ..read more
Visit website